11th Padma Bridge span installed

Send
Munshiganj Correspondent
Published : 11:00, Apr 23, 2019 | Updated : 11:04, Apr 23, 2019

11th span of Padma Bridge installed on Apr 23, 2019. BANGLA TRIBUNE/File PhotoThe 11th span of the Padma Bridge has been installed at Zajira point in Munshiganj on Tuesday (Apr 23).
The ‘Span 6C’ has been installed at the Zajira point on Tuesday, said Assistant Engineer of the Padma Bridge Project Humayun Kabir.
The span—150 metres long and weighing about 3,140 tons—was transported from Munshiganj’s Mawa Construction Yard to Shariatpur’s Zajira upazila point on Monday (Apr 22) morning by the Tiyan E crane, he added.
It is the 9th span installed at Zaria end, and the 11th span of the bridge.
A total of 41 spans—each 150-metres-long—have been placed on the 42 pillars of the 6.15 kilometre bridge.
So far, nine spans have been placed—on pillars 33, 34, 35, 36, 37, 38, 39, 40, 41 and 42— on the Zajira end of the bridge; and one more, span 3A, has been installed on the 13th and 14th pillars on the Mawa end.
One temporary span has been placed on pillars 5 and 6 on the Mawa end.